Trigon Provides Progress Update on the Restart of its Kombat Mine

*Plan On Schedule And On Budget*

TORONTO, ON / ACCESSWIRE / July 26, 2021 / Trigon Metals Inc. (TSXV:TM) ("Trigon" or the "Company") is pleased to provide an update on the progress of the various projects related to the restart of its Kombat Mine in Namibia, where open pit mining is planned to recommence in late 2021.

The Company is targeting initial production of 4,000t of copper in concentrate for the 2022 calendar year, by accessing ore from the open pit. Planned production is expected to increase to 14,500t of copper in concentrate in 2024, when higher grade underground ore will be accessed and the proposed upgrades to crushing and milling equipment are incorporated.

Onsite Activities

In May 2021, the Company announced the procurement of long lead items for the restart of the Kombat Mine, including an order to Xinhai (Yantai) Mining Engineering Co., Ltd for the procurement of new flotation cells. The manufacture of all long lead items is now well underway and shipping from China is anticipated during August 2021. Other long lead plant items have been ordered locally from Namibian and South African suppliers, and delivery of various key equipment items is planned for September and October 2021.

At the Kombat Mine, the preparation of the processing plant for the arrival of the new equipment is progressing well, with local contractors stripping old components from the plant and upgrading existing useable components and structures. The previously operational mine has significant office, workshop and other infrastructure already in place, this has been refurbished by local contractors. The use of this existing infrastructure has resulted in material cost savings for the Company in terms of its establishment capital.

Progress is also well underway on the construction of the new tailings storage facility ("TSF"), with the selected area having been cleared and now ready for next phase.

The Company has also made payment in full for the installation of a 2.5 MVA power supply to the mine and work on this installation will commence in due course.

Commenting, Jed Richardson, President and CEO of Trigon, said, "We are extremely pleased with the progress we have made at Kombat over the past few months. It has been exciting to see the site come alive with activity after many years on care and maintenance, and we are on track with both our timelines and budget as we target production by the end of this year. At current copper prices, the mine will create significant shareholder value; additionally, we are very positive about the long-term copper price and if it does continue to strengthen, the Kombat Mine provides strong leverage for long term gains for shareholders."

Approximately 80 contractors are currently on site working on the plant, offices and TSF establishment.

Trigon has appointed a senior management team at Kombat in addition to other key positions required at this stage of the restart process, such as a Health and Safety officer. Further appointments will be made by both the Company and the mining contractor over the next few months as the Company advances towards production.

NI 43-101 Mineral Resource Estimate Update and Mining

In early 2021, subsequent to the update of the Kombat mineral resource estimate in September 2020, Trigon undertook a resampling program on core retained from historic drilling of the Kombat area. Results of this program are currently being analyzed and modelled by the Company's technical consultants, Minxcon (Pty) Ltd, and the updated NI 43-101 compliant mineral resource estimate will be published once available. An updated feasibility study including a life of mine plan for the open pit will be undertaken once the updated Mineral Resource has been completed.

Open pit mining will be outsourced to a local contractor, and the Company is in final stages of contract negotiations with the selected contractor. Contractor equipment mobilization and site establishment is scheduled to start in August 2021.

Concentrate Purchaser Financing

The Company is in advanced stage discussions with a metal trading group for both a financing facility and concentrate offtake once the Kombat Mine is in production. Final terms are subject to due diligence and internal approvals by the metal trader and will be announced in due course.

About Kombat Mine

The Kombat Project is the flagship project of Trigon Metals Inc., with the Company's mining and prospecting licence areas covering an area of more than 7,500 ha in the Otavi Mountainlands in Namibia. The Kombat Project is comprised of three mining licences, which produced approximately 12.46 million tonnes of copper between 1962 and 2008, at a grade of 2.62%. The other two mining licences are within close proximity to Kombat at Gross Otavi and Harasib, which are believed to be highly prospective for lead and zinc. In addition, the Company also holds an interest in two exclusive prospecting licences, which represent a potential strike extension of Kombat.

Trigon Metals Inc.

Trigon is a publicly traded Canadian exploration and development company with its core business focused on copper and silver holdings in mine-friendly African jurisdictions. Currently the company has operations in Namibia and Morocco. In Namibia, the Company holds an 80% interest in five mining licences in the Otavi Mountainlands, an area of Namibia widely recognized for its high-grade copper deposits, where the Company is focused on exploration and re-development of the previously producing Kombat mine. In Morocco, the Company is the holder of the Silver Hill project, a highly prospective copper and silver exploration project.

Qualified Person

Mr. Uwe Engelmann(BSc (Zoo. & Bot.), BSc Hons (Geol.), Pr.Sci.Nat. No. 400058/08, MGSSA) of Minxcon, is a "qualified person" as such term is defined in NI 43-101 and has reviewed and approved the technical information and data included in this press release. As a director of Minxcon, Mr. Engelmann is considered independent.

Cautionary Notes

This news release may contain forward-looking statements. These statements include statements regarding the restart of the Kombat Mine, the Company's strategies, and the Company's abilities to execute such strategies, the Company's ability to obtain adequate financing, the Company's ability to build the requisite infrastructure at the Kombat Mine, the Company's ability to obtain the requisite equipment, the Company's expectations for the Kombat Project, and the Company's future plans and objectives. These statements are based on current expectations and assumptions that are subject to risks and uncertainties. Actual results could differ materially because of factors discussed in the management discussion and analysis section of our interim and most recent annual financial statements or other reports and filings with the TSX Venture Exchange and applicable Canadian securities regulations. We do not assume any obligation to update any forward-looking statements, except as required by applicable laws.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

For further information, contact:
Jed Richardson
+1 647 276-6002
jed.richardson@trigonmetals.com
Website: www.trigonmetals.com

SOURCE: Trigon Metals Inc.



View source version on accesswire.com:
https://www.accesswire.com/657013/Trigon-Provides-Progress-Update-on-the-Restart-of-its-Kombat-Mine

To view this piece of content from www.accesswire.com, please give your consent at the top of this page.

About ACCESS Newswire

DK

Subscribe to releases from ACCESS Newswire

Subscribe to all the latest releases from ACCESS Newswire by registering your e-mail address below. You can unsubscribe at any time.

Latest releases from ACCESS Newswire

U.S. Polo Assn. Expands Collegiate Partnership Program to Record 70 Teams for 2026 Season5.3.2026 13:00:00 CET | Press release

WEST PALM BEACH, FLA. / ACCESS Newswire / March 5, 2026 / U.S. Polo Assn., the official sports brand of the United States Polo Association (USPA), proudly announces the continued expansion of its Collegiate Partnership Program (CPP) for the 2026 season and academic year. Now in its eighth consecutive year, the program reaches a historic milestone by supporting 70 collegiate teams across 31 universities nationwide, the largest number of teams ever participating in the program.U.S. Polo Assn.'s Collegiate Partnership Program featuring the California Polytechnic State University Women's and Men's Polo Teams Photo Credit: California Polytechnic State University Polo Teams U.S. Polo Assn. will outfit hundreds of student-athletes from coast to coast, including small private and large public institutions, Ivy League Universities, and Historically Black Colleges and Universities (HBCUs). The CPP supports 35 women's and 35 men's teams, reinforcing U.S. Polo Assn.'s long-standing commitment to g

British Library Selects Preservica for Large-Scale Digital Preservation Program4.3.2026 15:00:00 CET | Press release

OXFORD, UK AND BOSTON, MA / ACCESS Newswire / March 4, 2026 / Preservica, the leader in AI-powered Active Digital Preservation™, today announced that it has been selected by the British Library to provide a Digital Preservation Repository solution and project implementation services to support the long-term preservation and management of the Library's extensive, petabyte- scale digital collections. Following a formal procurement and evaluation process, Preservica will deliver a secure, cloud-based Digital Preservation platform to support the continuous acquisition, management, and long-term preservation of the Library's diverse and expanding digital collections - including e-books, e-journals, sound recordings, UK websites, eTheses, digitised heritage materials and more - strengthening its ability to safeguard digital content for future generations. "Robust and secure Digital Preservation is essential for the effective custodianship, management and long-term readability of modern digit

Accu-Time Systems Announces Strategic Integration with Connecteam for Seamless Workforce Management4.3.2026 15:00:00 CET | Press release

The collaboration brings enterprise-grade stride80 time clocks to the Connecteam ecosystem, offering businesses a unified solution for high-accuracy attendance and real-time data sync. BOSTON, MASSACHUSETTS / ACCESS Newswire / March 4, 2026 / Accu-Time Systems (ATS), a leading provider of employee time collection solutions, today announced a strategic partnership with Connecteam, the all-in-one platform for managing distributed workforces. This collaboration integrates Connecteam's workforce management system with Accu-Time Systems' stride80 employee time clocks-delivering a unified, accurate, and secure way to collect employee time for payroll processing. Through this integration, employee punches recorded on stride80 time clocks are automatically transmitted to Connecteam's time tracking system in real time. The result is a streamlined data flow that eliminates manual entry, reduces payroll errors, and saves organizations valuable administrative time. "By integrating Connecteam's pla

Formerra Appoints Tom Kelly as Chief Executive Officer4.3.2026 14:00:00 CET | Press release

CLEVELAND, OHIO / ACCESS Newswire / March 4, 2026 / Formerra, LLC ("Formerra"), a leading distributor of engineered thermoplastic resins, additives, elastomers, and other specialty materials, today announced the appointment of Tom Kelly as Chief Executive Officer ("CEO"). A seasoned executive with over 30 years of specialty and engineered materials experience, Tom is known for leading teams to drive differentiated growth and building high-performing organizations set up for long-term success. The former CEO, Cathy Dodd, will stay on as Special Advisor to the Board and will remain an investor in the Company. Tom brings extensive commercial, supply chain, and distribution experience with a strong background in scaling global enterprises in the engineered materials sector. After previous roles at Cabot Microelectronics and Chemtura, Tom's most recent role was Senior Vice President of Engineered Materials at Celanese, where he led key commercial and operational initiatives across engineere

New GTDC Research Details Distribution's Influence on AI, Cloud and Hyperscaler Sales and Adoption3.3.2026 16:00:00 CET | Press release

IT distributors have become digital ecosystem orchestrators that unify cloud, AI, hyperscaler, and subscription-based business models. Distribution significantly accelerates vendor growth while reducing risk, allowing suppliers to scale efficiently, expand partner bases, enter new markets and mitigate financial and operational liabilities. Digital platforms are creating a new GTM "operating system". These systems offer end-to-end digital commerce and intelligence layers to manage procurement, billing, lifecycles and analytics. TAMPA, FL / ACCESS Newswire / March 3, 2026 / The Global Technology Distribution Council (GTDC), the world's largest consortium of technology distributors, has released a new research report, Distribution: The Digital Force Multiplier. Developed by CommCentric Solutions, this study examines how IT distribution has transformed and continues to evolve into a critical enabler of cloud, artificial intelligence (AI), hyperscaler and platform-driven business models acr

In our pressroom you can read all our latest releases, find our press contacts, images, documents and other relevant information about us.

Visit our pressroom
World GlobeA line styled icon from Orion Icon Library.HiddenA line styled icon from Orion Icon Library.Eye