Robust engineering design for key mine-site facilities reflects commitment to environmental leadership
VANCOUVER, BC / ACCESSWIRE / August 10, 2021 / Northern Dynasty Minerals Ltd. (TSX:NDM)(NYSE American:NAK) ("Northern Dynasty" or the "Company") reports that its 100%-owned US-based subsidiary Pebble Limited Partnership ("Pebble Partnership") has determined the 8.1 magnitude ("M") earthquake experienced in Alaska on July 28, 2021 resulted in substantially less ground movement at the project site than the seismic events considered in the assessment of the stability of its proposed tailings facility designs.
"We determined the 8.1 M earthquake that occurred last month south of the Alaska Peninsula, about 300 miles from our site, created ground acceleration at Pebble that is 20 - 30 times less than the design earthquakes we've evaluated," said Ron Thiessen, Northern Dynasty President & CEO. "To put that into perspective, the 8.1 M earthquake recorded July 28 is the largest seismic event in the United States in the past 50 years."
‘Seismic risk' is measured as ground acceleration as a proportion of gravity ("g"). The Pebble Partnership has assessed seismic risk at the Pebble site so that proposed tailings embankments and other mine facilities would not fail under even the most severe seismic events, which are extraordinarily unlikely. This is a course of action that will continue throughout the state permitting process and life of mine.
The extreme seismic events modeled to test the stability of proposed tailings embankments and other mine-site facilities at Pebble include:
- a repeat of the 9.2 M megathrust event that occurred in Alaska's Prince William Sound in 1964 (the second largest seismic event ever recorded);
- an 8.0 M earthquake occurring ~50 miles east of the Pebble Project site, similar to but of larger magnitude than the 7.1 M event that occurred north of Anchorage in November 2018;
- a 7.5 M event along the entire length of the Lake Clark Fault, including those portions closest to the Pebble site for which no evidence of movement for more than 10,000 years has been detected; and,
- a 6.5 M event occurring immediately below the proposed Pebble mine site, where no evidence of a fault exists.
"The highest ground acceleration at the Pebble site produced as a result of these potential, extreme seismic events is estimated to be 0.6 g (or 60% of the rate of acceleration due to gravity). It is these types of extreme ground movements that our proposed tailings facilities are designed to withstand," Thiessen explained. "By comparison, the extremely rare 8.1M event recorded last month created ground movement at Pebble of about 0.02 to 0.03 g, or 20 - 30 times less than what we have considered.
"When it comes to engineering and environmental solutions to protect the long-term integrity of downstream water quality and aquatic habitat, our solutions bring modern and technically sound performance standards for American mining," Thiessen said. "We're proud of it. We continue to believe it is the right approach for this important project in this unique location."
About Northern Dynasty Minerals Ltd.
Northern Dynasty is a mineral exploration and development company based in Vancouver, Canada. Northern Dynasty's principal asset, owned through its wholly owned Alaska-based U.S. subsidiary, Pebble Limited Partnership, is a 100% interest in a contiguous block of 2,402 mineral claims in southwest Alaska, including the Pebble deposit, located 200 miles from Anchorage and 125 miles from Bristol Bay. The Pebble Partnership is the proponent of the Pebble Project, an initiative to develop one of the world's most important mineral resources.
For further details on Northern Dynasty and the Pebble Project, please visit the Company's website at www.northerndynastyminerals.com or contact Investor services at (604) 684-6365 or within North America at 1-800-667-2114. Review Canadian public filings at www.sedar.com and U.S. public filings at www.sec.gov.
CONTACT:
Ronald W. Thiessen
President& CEO
U.S. Media Contact:
Dan Gagnier, Gagnier Communications
(646) 569-5897
Forward Looking Information and other Cautionary Factors
This release includes certain statements that may be deemed "forward-looking statements" under applicable law. All statements in this release, other than statements of historical facts, which address permitting, development and production for the Pebble Project are forward-looking statements. These statements include statements regarding (i) the mine plan for the Pebble Project, (ii) the social integration of the Pebble Project into the Bristol Bay region and benefits for Alaska, (iii) the political and public support for the permitting process, (iv) the ability to successfully appeal the negative Record of Decision and secure the issuance of a positive Record of Decision by the U.S. Army Corps of Engineers and the ability of the Pebble Project to secure state permits, (v) the right-sizing and de-risking of the Pebble Project, (vi) the design and operating parameters for the Pebble Project mine plan, (vii) exploration potential of the Pebble Project, (viii) future demand for copper and gold, (ix) the potential partnering of the Pebble Project, and (x) the ability and timetable of NDM to develop the Pebble Project and become a leading copper, gold and molybdenum producer. Although NDM believes the expectations expressed in these forward-looking statements are based on reasonable assumptions, such statements should not be in any way be construed as guarantees that the Pebble Project will secure all required government permits, establish the commercial feasibility of the Pebble Project or develop the Pebble Project. Assumptions used by NDM to develop forward-looking statements include the assumptions that (i) the Pebble Project will obtain all required environmental and other permits and all land use and other licenses without undue delay, (ii) studies for the development of the Pebble Project will be positive, (iii) NDM's estimates of mineral resources will not change, (iv) NDM will be able to establish the commercial feasibility of the Pebble Project, and (v) NDM will be able to secure the financing required to develop the Pebble Project. The likelihood of future mining at the Pebble Project is subject to a large number of risks and will require achievement of a number of technical, economic and legal objectives, including (i) obtaining necessary mining and construction permits, licenses and approvals without undue delay, including without delay due to third party opposition or changes in government policies, (ii) finalization of the mine plan for the Pebble Project, (iii) the completion of feasibility studies demonstrating that any Pebble Project mineral resources that can be economically mined, (iv) completion of all necessary engineering for mining and processing facilities, (v) the inability of NDM to secure a partner for the development of the Pebble Project, and (vi) receipt by NDM of significant additional financing to fund these objectives as well as funding mine construction, which financing may not be available to NDM on acceptable terms or on any terms at all. NDM is also subject to the specific risks inherent in the mining business as well as general economic and business conditions, such as the current uncertainties with regard to COVID-19.
The National Environment Policy Act Environmental Impact Statement process requires a comprehensive "alternatives assessment" be undertaken to consider a broad range of development alternatives, the final project design and operating parameters for the Pebble Project and associated infrastructure may vary significantly from that currently contemplated. As a result, the Company will continue to consider various development options and no final project design has been selected at this time.
For more information on the Company, Investors should review the Company's filings with the United States Securities and Exchange Commission and its home jurisdiction filings that are available at www.sedar.com
SOURCE: Northern Dynasty Minerals Ltd.
View source version on accesswire.com:
https://www.accesswire.com/659021/Pebble-Project-Facilities-Would-Be-Unaffected-by-Recent-81M-Earthquake-in-Alaska
To view this piece of content from www.accesswire.com, please give your consent at the top of this page.
About ACCESS Newswire
Subscribe to releases from ACCESS Newswire
Subscribe to all the latest releases from ACCESS Newswire by registering your e-mail address below. You can unsubscribe at any time.
Latest releases from ACCESS Newswire
Media Invitation: Fields Medals and Cutting-Edge Math at ICM 2026 in Philadelphia2.6.2026 20:30:00 CEST | Press release
PHILADELPHIA, PA / ACCESS Newswire / June 2, 2026 / Members of the press are invited to the world's most prestigious mathematics conference, which will take place at the Pennsylvania Convention Center in Philadelphia from July 23 to July 30, 2026. Held every four years, the International Congress of Mathematicians (ICM) includes the announcement of the field's top prizes - including the Fields Medals - as well as top talks from leading mathematicians on cutting-edge developments in the field. Staff reporters and freelance journalists can register to attend the conference free of charge through June 22. Media registration includes access to a press conference with the Fields Medalists and other honorees following their announcement during the July 23 opening ceremony. A press room will also be available during the conference. Discounted hotel room rates are available to attendees. For more information, visit the ICM 2026 website or email icmpressinquiries@simonsfoundation.org. The confe
IXOPAY Launches Payments Intelligence and IXONav, an AI Payments Assistant Built to Unlock Real-Time Insights Across the Payments Journey2.6.2026 06:00:00 CEST | Press release
Company's intelligence layer combines AI-driven analytics with anomaly detection to improve merchant payments optimization, performance and revenue outcomes LEHI, UT / ACCESS Newswire / June 2, 2026 / IXOPAY, the performance layer powering global payments for the agentic era, today announced IXOPAY Payments Intelligence, a unified control center that transforms fragmented payment data into real-time, actionable insights. The company also launched IXONav, a new AI agentic navigator built to unlock key insights at every step in the payments journey. By combining AI-driven analytics, anomaly detection and LLM agents, the platform helps merchants uncover optimization opportunities, improve routing performance, increase authorization rates and reduce per-transaction costs. IXOPAY's no-code payments platform unifies payment orchestration, tokenization, and intelligence, and provides merchants with a configurable infrastructure to optimize their payments performance. The IXOPAY Payments Intel
Clean Air Metals Files Audited Annual Financial Statements for the Year Ended January 31, 20262.6.2026 03:00:00 CEST | Press release
THUNDER BAY, ON / ACCESS Newswire / June 1, 2026 / Clean Air Metals Inc. ("Clean Air Metals" or the "Company") (TSX.V:AIR)(FRA:CKU)(OTCQB:CLRMF) announces that it has filed its audited consolidated financial statements and management's discussion and analysis for the year ended January 31, 2026, available for viewing on www.sedarplus.ca. Financial Highlights Total assets as at January 31, 2026 of $36,226,670 Total cash as at January 31, 2026 of $1,133,766 Working capital deficiency as at January 31, 2026 of $2,281,241 Shareholder's equity as at January 31, 2026 of $32,604,804 During the year ended January 31, 2026, the Company incurred $1,190,489 in cost for exploration activities at the TBN project. Early in the year, the Company's management team executed a successful drill program at the Current Deposit to delineate larger ballroom structures. This was followed up by a significant undertaking at the Escape Deposit down plunge, to reassess past MT data and refine drilling targets in
Graid Technology Launches VROC(TM) by Graid Technology with 24-Month Roadmap and Tier 1 OEM Support2.6.2026 02:00:00 CEST | Press release
VROC™ by Graid Technology brings active development, Intel® Xeon® 6 platform support, and no-cost upgrades to an established CPU-based NVMe RAID foundation. SUNNYVALE, CA / ACCESS Newswire / June 1, 2026 / Graid Technology, creator of SupremeRAID™ and global steward of Intel® VROC, today announced VROC™ by Graid Technology, a rebranded and actively developed platform with a 24-month roadmap delivering new features, expanded platform support, and long-term investment for existing and future customers. Intel® VROC has served as the CPU-based software RAID foundation for Intel-powered enterprise servers across Tier 1 platforms worldwide. Under Graid Technology's stewardship, the product transitions from sustained maintenance into active development with no disruption to existing deployments. The VROC™ by Graid Technology roadmap includes: Intel® Xeon® 6 platform support - including Oak Stream (Diamond Rapids) - with no-cost upgrades for existing Intel® VROC customers Hardware key eliminat
Karbon-X to Present at the Small Cap Growth Virtual Investor Conference June 4th1.6.2026 15:30:00 CEST | Press release
Company invites individual and institutional investors, as well as advisors and analysts, to attend online at VirtualInvestorConferences.com CALGARY, AB / ACCESS Newswire / June 1, 2026 / Karbon-X Corp. (OTCQB:KARX), based in Calgary, Alberta focused on global carbon markets and climate infrastructure solutions, today announced that Chad Clovis, Chief Executive Officer will present live at the Small Cap Growth Virtual Investor Conference hosted by VirtualInvestorConferences.com, on June 4, 2026 DATE: June 4th TIME: 10:00 AM ET REGISTER HERE Available for 1x1 meetings: June 5th-9th Schedule 1x1 Meetings here. This will be a live, interactive online event where investors are invited to ask the company questions in real-time. If attendees are not able to join the event live on the day of the conference, an archived webcast will also be made available after the event. It is recommended that online investors pre-register and run the online system check to expedite participation and receive
In our pressroom you can read all our latest releases, find our press contacts, images, documents and other relevant information about us.
Visit our pressroom