VANCOUVER, BC / ACCESSWIRE / July 22, 2021 / Granite Creek Copper Ltd. (TSX.V:GCX)(OTCQB:GCXXF) ("Granite Creek" or the "Company") is pleased to announce the first tranche of assays from Phase 1 of the Company's 2021 drilling program on its 100%-owned Carmacks project. This recently completed first phase consisted of nineteen diamond drill holes, totalling 6355 meters, focused on the existing resource area with the goals of strengthening confidence in the resource model, evaluating opportunities for resource expansion and/or upgrading the sulphide portion of Zones 1 and 2000S from an inferred to indicated resource, and evaluating continuity of mineralization in Zone 13 (Figure 1).
Granite Creek President & CEO, Tim Johnson, commented, "The Company is extremely pleased with the progress of 2021 exploration program at Carmacks. A Phase 3 drilling program is under development and projected to commence in mid-August of this year. The addition of this third stage would expand the overall 2021 campaign to include a total of 10,000 meters of diamond drilling as well as 3000m of reverse circulation drilling. We expect this program will significantly expand the total contained metal on the project, resulting in a substantially and form the basis for a new Preliminary Economic Assessment."
Table 1 - Highlights from first tranche of 2021 Diamond Drill Assays at the Carmacks Project
Drillhole | From (m) | To (m) | Length* (m) | Cu (%) | Mo (%) | Au (g/t) | Ag (g/t) | CuEq** (%) | Zone |
|---|---|---|---|---|---|---|---|---|---|
CRM21-004 | 323.50 | 367.00 | 43.50 | 1.12 | 0.03 | 0.20 | 3.41 | 1.40 | Zone 1 |
Including | 338.50 | 367.00 | 28.50 | 1.57 | 0.04 | 0.29 | 4.53 | 1.96 | |
and including | 352.00† | 367.00 | 15.00 | 1.80 | 0.07 | 0.33 | 4.81 | 2.31 | |
CRM21-007 | 222.52 | 223.70 | 4.08 | 0.91 | 0.01 | 0.19 | 6.32 | 1.13 | |
CRM21-010 | 450.00 | 513.40 | 63.40 | 0.27 | BDL | 0.08 | 1.31 | 0.35 | |
Including | 450.00 | 482.25 | 32.25 | 0.30 | BDL | 0.08 | 1.41 | 0.39 | |
Including | 478.32 | 482.25 | 3.93 | 0.58 | 0.01 | 0.20 | 2.85 | 0.78 | |
Including | 488.90 | 513.40 | 24.50 | 0.30 | BDL | 0.09 | 1.47 | 0.39 | |
including | 502.90 | 509.75 | 6.85 | 0.41 | 0.01 | 0.16 | 1.93 | 0.57 | |
2000 S | |||||||||
CRM21-003 | 146.35† | 214.50 | 68.15 | 0.59 | 0.03 | 0.14 | 3.69 | 0.830 | |
Including | 161.40 | 179.80 | 18.04 | 0.81 | 0.03 | 0.21 | 4.80 | 1.13 | |
CRM21-005 | 137.05 | 179.80 | 43.24 | 0.74 | 0.05 | 0.16 | 3.82 | 1.06 | |
Including | 142.05 | 158.40 | 16.35 | 1.20 | 0.03 | 0.26 | 6.11 | 1.58 | |
CRM21-006 | 194.40 | 278.20 | 83.80 | 0.64 | 0.01 | 0.13 | 3.23 | 0.81 | |
Including | 229.20 | 278.20 | 49 | 0.87 | 0.02 | 0.17 | 3.88 | 1.10 | |
Including | 248.76 | 266.20 | 17.44 | 1.21 | 0.03 | 0.22 | 5.11 | 1.53 | |
CRM21-008 | 195.80 | 228.40 | 32.6 | 0.80 | 0.02 | 0.17 | 3.88 | 1.02 | |
Including | 201.55 | 215.55 | 14 | 1.10 | 0.02 | 0.24 | 4.86 | 1.40 | |
CRM21-009 | 190.50 | 243.85 | 53.35 | 0.59 | 0.01 | 0.14 | 2.71 | 0.75 | |
Including | 191.30 | 201.70 | 10.4 | 0.87 | BDL | 0.25 | 3.70 | 1.09 | |
and including | 209.00 | 225.95 | 16.95 | 0.62 | 0.01 | 0.13 | 2.76 | 0.77 | |
and Including | 229.90 | 235.25 | 5.35 | 1.21 | 0.06 | 0.28 | 4.88 | 1.68 |
** Copper equivalent (Cu Eq) values assume Cu $3.35/lb, Au $1600/oz, Ag $24/oz, Mo $12/lb and 100% recovery. *Weighted average intercepts shown. Estimated true widths vary but, based on geological interpretation of cross-sections, are estimated to be typically 60-70% of the intersected widths. † Zone has poor recovery
Figure 1 - Carmacks Copper Project Plan View
To view this piece of content from www.accesswire.com, please give your consent at the top of this page.Zone 1
Eight holes were drilled in Zone 1 with the objective of increasing confidence in the inferred portion of the sulfide resource of this zone as well as evaluating the southern down-dip continuation of the inferred resource (Figure 2). The drilling was successful in achieving its objectives of delineating the depth extent of mineralization, expanding the mineralization below the current resource model and confirming the grade and anticipated thickness in the inferred portion of the sulphide resource in this zone.
Table 2 - Zone 1 mineral resource[1]
Category | Tonnes (000's) | Cu (%) | Acid soluble Cu (%) | Sulphide Cu (%) | Au (g/t) | Ag (g/t) |
Measure & Indicated Oxide | 11,980,000 | 1.07 | 0.86 | 0.21 | 0.46 | 4.58 |
Inferred Oxide | 90,000 | 0.73 | 0.53 | 0.20 | .13 | 1.81 |
Measure & Indicated Sulfide | 4,340,000 | 0.75 | 0.03 | 0.72 | 0.22 | 2.33 |
Inferred Sulfide | 4,031,000 | 0.71 | 0.01 | 0.70 | .18 | 1.90 |
1 Mineral resource prepared by Dr. Gilles Arseneau, P.Geo., reported in JDS Energy and Mining Inc 2017 Ni 43-101 [1] JDS Energy and Mining. Feb 9, 2017. NI 43-101 Preliminary Economic Assessment Technical Report on the Carmacks Project, Yukon, Canada., with updated resource for Zones 2000S, 12 and 13 as reported in April 9, 2018 by Copper North Mining.
While the Preliminary Economic Assessment ("PEA") published in 2017(1,2) only looked at the oxide material in Zones 1,4 & 7, work being conducted by Sedgman and Mining Plus (see news release dated May 18, 2021) is looking at various scenarios to process the sulfide portion of Zone 1 and other sulfide zones of the deposit building a basis for an updated PEA that would include both oxide and sulfide ore.
Figure 2 - Long section of Zone 1 looking west
To view this piece of content from www.accesswire.com, please give your consent at the top of this page.Zone 2000S
Zone 2000S, originally discovered in 2006 as the result of an IP survey, has the potential to add tonnage in the sulfide domain of resource category. The mineral resource on this zone is shown in Table 3, which was based on a 0.25% total copper grade cut-off.1 Six diamond drillholes were drilled in this zone are part of the first phase of drilling with the intent of evaluating the continuation of bornite-chalcopyrite mineralization down dip. The drilling was very successful in not only confirming the continuation of the high grade bornite-chalcopyrite mineralization but also extending mineralization well below the current block model as well as encountering significant molybdenite mineralization A technical hole (CRM21-018) was drilled subparallel to the mineralization to evaluate the geological concept of a southern W-E striking fault which post-dates and offsets mineralization.
Table 3 - Zone 2000S mineral resources1
Category | Tonnes (000's) | Cu (%) | Acid soluble Cu (%) | Sulphide Cu (%) | Au (g/t) | Ag (g/t) |
Measure & Indicated Oxide | 410,878 | 0.64 | 0.49 | 0.14 | 0.23 | 3.15 |
Inferred Oxide | 266,894 | 0.57 | 0.34 | 0.24 | 0.14 | 2.66 |
Measure & Indicated Sulfide | 740,000 | 0.70 | 0.07 | 0.63 | 0.17 | 3.28 |
Inferred Sulfide | 636,000 | 0.73 | 0.05 | 0.68 | 0.18 | 3.50 |
1Mineral resource prepared by Dr. Gilles Arseneau, P.Geo., reported in JDS Energy and Mining Inc 2017 Ni 43-101 [1] JDS Energy and Mining. Feb 9, 2017. NI 43-101 Preliminary Economic Assessment Technical Report on the Carmacks Project, Yukon, Canada., with updated resource for Zones 2000S, 12 and 13 as reported in April 9, 2018 by Copper North Mining.
Figure 3 - Long section of 2000S
To view this piece of content from www.accesswire.com, please give your consent at the top of this page.Zone 13
Three diamond drill holes were completed in Zone 13 with the intent of evaluating the northern continuity of sulfide mineralization, along strike and to infill an open area of the block model. Within 1000m of Zone 1, Zone 13 has the potential to add both oxide and sulfide resources to an updated mine plan. The sulfide portion remains open along strike and at depth. All assay results from Zone 13 are pending.
COVID-19 Protocols
Granite Creek has worked closely with the Yukon government to develop a COVID-19 safety plan that enables the Company to implement an effective work plan while maintaining the highest degree of safety of our workers and surrounding communities. The Company strictly adheres to mandates put in place by health authorities at the Federal and Territorial government level and hold the health and safety of our workers, and the citizens of the communities in which work in the highest regard.
[1] JDS Energy and Mining. Feb 9, 2017. NI 43-101 Preliminary Economic Assessment Technical Report on the Carmacks Project, Yukon, Canada. Contained metal based on 23.76 million tonnes of NI 43-101 compliant resources in the Measured and Indicated categories grading 0.85% Cu, 0.31 g/t Au, 3.14 g/t Ag.
[2] Arseneau Consulting Services, 2016 Independent Technical Report on the Carmacks Copper Project, Yukon, Canada.
About Granite Creek Copper
Granite Creek, a member of the Metallic Group of Companies, is a Canadian exploration company focused on the 176 square kilometer Carmacks project in the Minto copper district of Canada's Yukon Territory. The project is on trend with the high-grade Minto copper-gold mine, operated by Minto Explorations Ltd, to the north and features excellent access to infrastructure with the nearby paved Yukon Highway 2, along with grid power within 12 km. More information about Granite Creek Copper can be viewed on the Company's website at www.gcxcopper.com.
FOR FURTHER INFORMATION PLEASE CONTACT:
Timothy Johnson, President & CEO
Telephone: 1 (604) 235-1982
Toll Free: 1 (888) 361-3494
E-mail: info@gcxcopper.com
Website: www.gcxcopper.com
Qualified Person
Ms. Debbie James, P.Geo., a qualified person for the purposes of National Instrument 43-101, has reviewed and approved the technical disclosure contained in this news release.
Quality Control and Quality Assurance
Quality assurance and quality control procedures include the systematic insertion of duplicate, blank and standard samples, making up 12% of the sample stream. Drill core samples were sawn in half, labelled, placed in sealed bags and shipped directly to the Bureau Veritas preparation laboratory in Whitehorse. All geochemical analyses were performed by Bureau Veritas in Vancouver. Copper and silver analysis was performed by four-acid digestion with an ICP-ES finish. Non-sulphide copper was determined through a sulphuric acid leach with an AAS finish. Gold was analyzed by igniting a 15 g sample followed by an aqua regia digestion with an ICP-MS finish.
Forward-Looking Statements
This news release includes certain statements that may be deemed "forward-looking statements". All statements in this release, other than statements of historical facts including, without limitation, statements regarding potential mineralization, historic production, estimation of mineral resources, the realization of mineral resource estimates, interpretation of prior exploration and potential exploration results, the timing and success of exploration activities generally, the timing and results of future resource estimates, permitting time lines, metal prices and currency exchange rates, availability of capital, government regulation of exploration operations, environmental risks, reclamation, title, and future plans and objectives of the company are forward-looking statements that involve various risks and uncertainties. Although Granite Creek Copper believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements. Forward-looking statements are based on a number of material factors and assumptions. Factors that could cause actual results to differ materially from those in forward-looking statements include failure to obtain necessary approvals, unsuccessful exploration results, changes in project parameters as plans continue to be refined, results of future resource estimates, future metal prices, availability of capital and financing on acceptable terms, general economic, market or business conditions, risks associated with regulatory changes, defects in title, availability of personnel, materials and equipment on a timely basis, accidents or equipment breakdowns, uninsured risks, delays in receiving government approvals, unanticipated environmental impacts on operations and costs to remedy same, and other exploration or other risks detailed herein and from time to time in the filings made by the companies with securities regulators. Readers are cautioned that mineral resources that are not mineral reserves do not have demonstrated economic viability. Mineral exploration and development of mines is an inherently risky business. Accordingly, the actual events may differ materially from those projected in the forward-looking statements. For more information on Granite Creek Copper and the risks and challenges of their businesses, investors should review their annual filings that are available at www.sedar.com.
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
SOURCE: Granite Creek Copper Ltd.
View source version on accesswire.com:
https://www.accesswire.com/656616/Granite-Creek-Copper-Reports-First-Results-from-Phase-1-of-2021-Drill-Program-Including-4350-Meters-of-140-Copper-Equivalent-at-the-Carmacks-Copper-Gold-Silver-Project-in-Yukon-Canada
To view this piece of content from www.accesswire.com, please give your consent at the top of this page.
About ACCESS Newswire
Subscribe to releases from ACCESS Newswire
Subscribe to all the latest releases from ACCESS Newswire by registering your e-mail address below. You can unsubscribe at any time.
Latest releases from ACCESS Newswire
Iggy Azalea Invests in Shift - The AI Company Behind the Fastest-Growing Platform in the $1.3 Trillion Creator Economy, Fanvue27.8.2026 14:00:00 CEST | Press release
The Grammy-nominated artist and entrepreneur has made a significant investment in SHIFT, whose AI infrastructure has propelled its flagship platform, Fanvue, from a $4m to $200m annualised run rate in just over 2 years. LONDON, UK / ACCESS Newswire / August 27, 2026 / Iggy Azalea, the four-time Grammy-nominated artist, entrepreneur, and active investor, has personally invested a substantial sum in Fanvue's parent company SHIFT - the AI infrastructure the platform runs on. As part of the investment deal, Azalea will also become the founding member of SHIFT's Creator Advisory Board. The move comes at a time when the world's biggest creators, athletes and music artists are increasingly looking to multi-million-dollar equity opportunities in the creator economy - recent examples include MrBeast and the Paul brothers, Jake and Logan. AI is transforming how people make money online. For two decades, the creator economy has run on a simple trade: creators build the audience, and advertisers r
ZAGENO and ORO Labs Partner to Connect Scientific Purchasing with Enterprise Procurement26.8.2026 14:35:00 CEST | Press release
Partnership combines ORO Labs' AI-native procurement orchestration platform with ZAGENO's scientific marketplace and supplier network to deliver a governed, end-to-end purchasing experience for life sciences R&D. BOSTON, MA / ACCESS Newswire / August 26, 2026 / ZAGENO, the scientific procurement platform connecting researchers with 75 million laboratory products from approximately 5,500 suppliers, today announced a strategic partnership with ORO Labs, the AI-native procurement orchestration platform. The partnership connects ORO Labs' enterprise intake, workflow, and approval capabilities with ZAGENO's scientific product discovery, marketplace, supplier network, and fulfillment infrastructure. Together, the companies enable a single governed journey from request and approval through product selection, ordering, and fulfillment. Scientific R&D procurement has specialized requirements. Researchers need fast, intuitive access to highly specific products, while procurement teams need polic
Eudia Accelerates Enterprise AI Transformation with Google Cloud's Gemini Enterprise for Legal25.8.2026 15:50:00 CEST | Press release
PALO ALTO, CA / ACCESS Newswire / August 25, 2026 / Eudia, the augmented intelligence platform for enterprise legal, contracting, and compliance, today announced a partnership with Google to launch new industry-specific AI capabilities on Google Cloud's Gemini Enterprise for Legal. Eudia's agent scales the legal, contracting, and compliance expertise of an organization's top operators to every team in the enterprise. Built on Google's Agent Development Kit and connected via MCP, Eudia combines a suite of specialized agents with digital twins of domain-scoped institutional knowledge, orchestrated with legal-specific reasoning and access to legal databases. Eudia enables Legal, Compliance, Procurement, and Revenue teams to draft and review contracts, analyze marketing assets for compliance, assess risk across thousands of executed contracts, and manage obligations across the entire company portfolio, giving large enterprises a faster path to trusted, governed legal AI. In practice, this
Envision Pharma Group Names Ryan Tubbs, Senior Vice President, Commercial Growth25.8.2026 15:00:00 CEST | Press release
New role unifies sales enablement, lead generation, and marketing under centralized leadership and expands oversight to customer success, supporting a consistent, connected client experience across Envision. FAIRFIELD, CT / ACCESS Newswire / August 25, 2026 / Envision Pharma Group (Envision) has appointed Ryan Tubbs as Senior Vice President, Commercial Growth. In this newly created role, Tubbs will lead the centralized Commercial Growth function spanning sales enablement, lead generation, marketing, and client success. He will also help shape Envision's commercial strategy and operating model to accelerate enterprise growth. Tubbs' remit also includes the Client Implementation and Client Experience teams. Connecting Envision's pre-sale and post-sale capabilities will create a more integrated commercial engine, making it easier for teams to bring the best of Envision to clients and for clients to realize value quickly. The timing is notable as Envision's iEnvision®, market access, and m
Polaris Renewable Energy Announces Renewal of Normal Course Issuer Bid25.8.2026 13:50:00 CEST | Press release
TORONTO, ON / ACCESS Newswire / August 25, 2026 / Polaris Renewable Energy Inc. (TSX:PIF) ("Polaris" or the "Company") today announced that the Toronto Stock Exchange ("TSX") has accepted its notice of intention to renew its normal course issuer bid ("NCIB"). The Company's Board of Directors believes that an NCIB represents an appropriate and desirable use of its available free cash to increase shareholder value and is in the best interest of the Company and its shareholders. Pursuant to the notice, Polaris may purchase up to 2,021,205 of its common shares ("Shares"), representing approximately 10% of the public float of 20,212,059 Shares as at August 13, 2026, during the twelve month period commencing August 27, 2026 and ending August 26, 2027, provided that the board of directors of Polaris has initially limited the NCIB to repurchase up to 176,872 Shares. As at August 13, 2026, there were 20,895,285 Shares issued and outstanding. Under the NCIB, other than purchases made under block
In our pressroom you can read all our latest releases, find our press contacts, images, documents and other relevant information about us.
Visit our pressroom