To continue operating the power grid safely and reliably in the future, GE Renewable Energy’s Grid Solutions business (NYSE: GE) and the transmission system operator TransnetBW have signed a contract for a turnkey solution to redesign the Pulverdingen 380 kV substation in the vicinity of Markgröningen, about 15 km northwest of Stuttgart.
The Pulverdingen substation needs to be redesigned for larger capacities and greater power fluctuations. As part of this redesign, the substation’s almost 50-year-old switchgear, will be upgraded and expanded during operation.
To support TransnetBW’s priorities to ramp up capacity, GE’s Grid Solutions team will design, produce, supply and commission 26 bays of 380 kV air-insulated switchgear (AIS) with associated buildings and control cabinets. Also in the plan is a 380 kV cable connection between the 380 kV/220 kV transformer and respective 380 kV switch panel. The overhead line connection to the substation will be executed in three phases. The erection of temporary overhead lines for several years is required in some cases to ensure safe operation of the switchgear during the construction period. The construction work is expected to take one decade, until the end of 2033.
This contract for a turnkey solution aligns with GE’s commitment to provide scalable power solutions to its customers that support the transformation of their electricity grids. The upgrade and expansion of the Pulverdingen substation will significantly improve short-circuit resistance, transmission capacity and voltage control.
"The Pulverdingen substation will strengthen the security of power supply in the Stuttgart area in the long term," said Christopher Kunstmann, project manager at TransnetBW.
“TransnetBW’s expansion plans for Germany’s electricity grid will provide a better network resiliency and power supply security in this region,” said Philippe Piron, CEO of GE Grid Solutions and Power Conversion. “For our team, this agreement represents not only our deep commitment to support TransnetBW in Germany but constitutes the example of the long-term partnerships GE Grid Solutions wants to adopt with key European customers, implementing key regional infrastructure to deliver reliable, stable and efficient energy transmission.”
GE Grid Solutions provides complete, engineered solutions for high voltage (HV) substations to power generation companies, utilities, and industries, bringing together the right mix of high-voltage products through expert engineering and full project management.
To view this piece of content from cts.businesswire.com, please give your consent at the top of this page.
View source version on businesswire.com: https://www.businesswire.com/news/home/20221215005043/en/
About Business Wire
Subscribe to releases from Business Wire
Subscribe to all the latest releases from Business Wire by registering your e-mail address below. You can unsubscribe at any time.
Latest releases from Business Wire
ABB Robotics and PSYONIC Use Human-Generated Data to Advance Robotic Dexterity16.6.2026 06:01:00 CEST | Press release
ABB Robotics and PSYONIC collaborate to revolutionize grasping and dexterity, a core capability for Autonomous Versatile Robotics™ ABB GoFa™ helps test PSYONIC’s Ability Hand for robotics, combining touch sensing, compliant design and human-derived training data Dexterity remains a major challenge for industry; improved handling can reduce engineering time by up to 30%¹ ABB Robotics is collaborating with California bionics company, PSYONIC, to advance robotic gripping and dexterity using a new approach that utilizes real-world manipulation data from human prosthetic use. By combining the PSYONIC Ability Hand with an ABB GoFa™ cobot, the collaboration will explore how touch and motion data generated by human prosthetic use can be used to train robots to perform delicate, variable tasks that have traditionally been difficult to automate. This press release features multimedia. View the full release here: https://www.businesswire.com/news/home/20260612749544/en/ “Human dexterity and the i
Signaloid Announces Availability of Amazon AWS Machine Image (AMI) for Accelerating Compute Workloads Ranging from Finance to Reinforcement Learning16.6.2026 06:00:00 CEST | Press release
British computing technology company Signaloid today announced the release of the Signaloid Compute Engine Amazon Machine Image (AMI) via AWS Marketplace. The release enables organizations to deploy Signaloid’s distribution-extended compute hardware (UxHw®) technology within their Amazon Virtual Private Clouds (VPCs). The AMI provides access to UxHw, which delivers orders-of-magnitude performance improvements on x86_64 and ARM (AArch64) AWS Elastic Compute Cloud (EC2) instances. Without requiring software rewrites, UxHw enables existing applications to compute directly on probability distributions, automating algorithms such as Monte Carlo methods in finance and physics, importance sampling in reinforcement learning, and particle filters in physical AI and robotics. The technology works through binary translation and optimization at the LLVM intermediate representation (LLVM IR) level, with optional hardware acceleration via FPGAs and Signaloid’s C0-ASIC that was recently taped-out in
Murata Collaborates with Synopsys to Provide Simulation Models Through Ansys Electromagnetic and Thermal Analysis Tools16.6.2026 04:00:00 CEST | Press release
Murata Manufacturing Co., Ltd. (TOKYO: 6981) (ISIN: JP3914400001) announces a new collaboration with Synopsys, Inc., enabling users of Synopsys' simulation tools to navigate directly to Murata's website to access and download the latest high-performance simulation models from Murata. The collaboration covers Synopsys' 3D electromagnetic field analysis tool Ansys HFSS™ and thermal analysis tool Ansys Icepak®, and marks a significant step toward streamlining the simulation workflow for electronic circuit designers. Murata is also the first company to offer passive component simulation models via Ansys Icepak*. This press release features multimedia. View the full release here: https://www.businesswire.com/news/home/20260615241645/en/ [Murata Manufacturing Co., Ltd.] New collaboration with Synopsys As demand for high-speed, high-capacity communications continues to grow, electronic circuit design has become increasingly complex. Engineers must now account for a range of physical phenomena
Trimontium Launches with $1.5 billion in AUM, Redefining Flexible CapitalSolutions16.6.2026 01:01:00 CEST | Press release
Founded by former Blackstone executive Vlado Spasov, Trimontium is an institutionally backed alternative asset manager purpose-built to deliver flexible capital solutions across Europe and North America Trimontium (the “Firm”), an institutionally backed alternative asset manager specialising in flexible capital solutions, today announced its launch with $1.5 billion in assets under management. The Firm’s investment approach is rooted in credit and special-situations expertise, with the flexibility to originate and execute tailored financing solutions across the full capital structure for a wide range of corporate needs. This press release features multimedia. View the full release here: https://www.businesswire.com/news/home/20260615892895/en/ Trimontium Founder and CIO, Vlado Spasov Founded by former Blackstone executive Vlado Spasov, Trimontium is one of the largest first-time alternative asset managers based in Europe focused on flexible capital solutions to launch, according to ava
Newmont Announces Key Executive Appointments for the Next Phase of Delivery15.6.2026 23:20:00 CEST | Press release
Newmont Corporation (NYSE: NEM, ASX: NEM, PNGX: NEM) (“Newmont”) today announced leadership appointments that further shape its go-forward Executive Leadership Team under President and Chief Executive Officer Natascha Viljoen and reflect the depth of leadership talent within the company. Effective July 1, 2026, Brian Tabolt has been appointed Chief Financial Officer, Mark Rodgers has been appointed Chief Operating Officer, and David Thornton has been appointed Chief Technical Officer. In addition, David Fry has been promoted to Executive Vice President, Project Development, reflecting the importance of disciplined project development and execution as Newmont advances its highest-return growth opportunities. This press release features multimedia. View the full release here: https://www.businesswire.com/news/home/20260615487768/en/ Mark Rodgers - COO “These appointments bring together respected leaders with deep industry experience and a strong understanding of our operational, financia
In our pressroom you can read all our latest releases, find our press contacts, images, documents and other relevant information about us.
Visit our pressroom