The Danish Energy Agency opens tenders for three new Danish offshore wind farms
Today the Danish Energy Agency is announcing tenders for three areas for the establishment of at least 2.8 GW of offshore wind power. The tenders are based on thorough market dialogues and includes, among other things, state subsidies and greater flexibility for developers to increase the likelihood of qualified bids.

The Danish Energy Agency is now offering three areas for the establishment of offshore wind power. These are ‘North Sea Mid’, ‘Hesselø’ in the Kattegat and ‘North Sea South’. In total, the wind power farms will be able to supply green electricity equivalent to the consumption of around three million Danish and European homes.
The three offshore wind farms are being offered with a support scheme known as a 2-sided capability-based contract for difference (CfD). Under this scheme, the state guarantees offshore wind producers a fixed price for their electricity. This reduces the risk of low electricity prices for developers - an element that has been requested by the market. In total a payment cap of DKK 55.2 billion including VAT has been set for the state.
The tenders contain requirements relating to sustainability and social responsibility, including requirements concerning the recyclability of the turbine blades, requirements against social dumping, and the winning bidder for ‘Hesselø’ must establish the offshore wind farm with a so-called nature-inclusive design. In order to guard against security threats, The Danish Energy Agency is at all times entitled to request the winning bidder to document compliance with applicable regulation on cybersecurity.
The tenders are a follow-up to the offshore wind tenders from 2024, where six areas were put up for tender. By the end of deadline for the first three areas, the Danish Energy Agency had not received any bids. Subsequently, The Danish Energy Agency has held several market dialogues, which formed the basis for two political agreements in 2025. The new 2.8 GW offshore wind tenders are based on these agreements.
The tender material is published via EU Supply. The deadline for submission of tenders for ‘North Sea Mid’ and ‘Hesselø’ is spring 2026. The deadline for submission of tenders for ‘North Sea South’ is autumn 2028.
Please note that there is a delay of up to 48 hours from publication until the links and thus the material is accessible.
Facts about the three offshore wind areas:
- ‘North Sea Mid’, minimum 1 GW, must be completed by the end of 2032
- ‘Hesselø’ in the Kattegat, minimum 800 MW, must be completed by the end of 2032
- ‘North Sea South’, minimum 1 GW, must be completed by the end of 2034
- The tenders will further enable the winning bidders to establish overplanting capacity.
Links:
EU Supply:
- Procurement material North Sea Mid
- Procurement material Hesselø
- Procurement material North Sea, South
Political Agreements:
- Agreement on tender framework for three offshore wind farms May 2025 (Danish)
- Adjustments to the above agreement October 2025 (Danish)
Contacts
Press contact (phone calls only)
Tel:+45 33 95 08 00presse@ens.dkImages

About Danish Energi Agency
The Danish Energy Agency works for a sustainable future. We are responsible for cost-effective and secure supply of electricity, gas, heating, water, telecoms and waste management. Our objective is to realize an intelligent green transition, where Denmark is a front runner and Danish experience can serve as inspiration to countries around the globe.
Subscribe to releases from Danish Energy Agency
Subscribe to all the latest releases from Danish Energy Agency by registering your e-mail address below. You can unsubscribe at any time.
Latest releases from Danish Energy Agency
Danish tender for CO₂ capture and storage enters next phase27.8.2025 14:45:00 CEST | Pressemeddelelse
The deadline for submitting initial bids for Denmark’s CO₂ capture and storage funding scheme has passed. The Danish Energy Agency is now entering into dialogue with the bidders ahead of the deadline for submitting final bids for the DKK 28.7 billion fund.
10 companies selected to compete for Denmark’s CCS Fund with DKK 28.7 billion for Carbon Capture and Storage16.5.2025 10:02:30 CEST | Pressemeddelelse
The Danish Energy Agency has selected 10 companies from a pool of 16 applicants to compete for DKK 28.7 billion in funding for Carbon Capture and Storage projects. The funding is expected to help reduce Denmark’s annual CO₂ emissions by 2.3 million tonnes from 2030.
Great interest in Denmark’s CCS fund: 16 companies want to apply26.3.2025 10:30:00 CET | Pressemeddelelse
The CCS fund for carbon capture and storage is DKK 28.7 billion, and a maximum of 10 companies can participate. To apply for funding, applicants must first be prequalified. 16 companies have applied, and the Danish Energy Agency will now assess the applications in order to select 10 companies.
Two companies want to store CO2 in the Danish subsurface7.3.2025 08:01:00 CET | Pressemeddelelse
The Danish Energy Agency (DEA) has received two applications from companies that want to explore the potential for storing CO2 in the subsurface in the nearshore areas Inez, Lisa og Jammerbugt offshore.
Danish Energy Agency publishes results from the market dialogue on 3 GW offshore wind28.2.2025 11:35:45 CET | Nyhed
The Danish Energy Agency publishes a memo with the results of the market dialogue that the Minister for Climate, Energy and Utilities asked the agency to conduct to investigate the background for the outcome of the 3 GW offshore wind procurement in the North Sea.
In our pressroom you can read all our latest releases, find our press contacts, images, documents and other relevant information about us.
Visit our pressroom