New Industry Guideline on Seafastening: Accelerates Offshore Wind Deployment and Saves Tons of Steel
As wind turbines grow larger and heavier, the equipment for securing them during transportation becomes more complex and expensive.

The WIS – Wind Industry Standardization project was initiated in late 2023. Now its first result is launched: the WIS Seafastening Design Guideline.
Led by Siemens Gamesa and Vestas, this industry-wide initiative introduces a common standard for seafastening design of wind turbine components on the installation vessels.
Thousands of tons of steel
A modern wind turbine installation vessel carrying five or six turbines at a time requires several thousand tons of steel on the deck in seafastening structures to keep nacelles, towers and blades secure on the transit from the harbor to the installation site.
With the new guideline, seafastening can be reused across multiple projects, reducing the amount of steel scrapped, the hours spent on design, manufacturing, certification, etc.
At the same time, it has the potential to significantly reduce vessel modification time between projects - helping to reduce a well-recognised bottleneck in the industry and directly accelerating offshore wind deployment.
"Standardizing seafastening is a logical step that benefits the entire industry without compromising competition. After a year of dedicated work, we are proud to see these guidelines being adopted," says Brian Mikkelsen, SVP, Nacelles R&D from Vestas.
Siemens Gamesa highlights the operational impact:
"This means fewer days spent in port and more time at sea installing turbines. It directly improves the speed and efficiency of offshore wind deployment," says Jesper Møller, Chief Engineer Offshore Execution from Siemens Gamesa.
Broad Industry Support
Ørsted’s installation projects are among the first to implement the guideline:
"We appreciate the effort made by the OEM’s and it is a significant step in the right direction for our industry. We will work on incorporating the WIS Seafastening Design Guideline into our upcoming projects and look forward to realizing its benefits across the supply chain," says Charlotte Krogh, Head of Offshore Construction & Logistics from Ørsted.
Havfram, a key offshore installation and marine services provider, emphasizes the significance of seafastening standardization:
"This initiative enables us to serve our customers even better by being able to offer better flexibility and directly contributes to reducing the industry's carbon footprint," says Håkon Halseth Johannessen, Head of Engineering & Technology from Havfram.
The guideline has been developed with support from key industry players, including Havfram, Cadeler, Fred Olsen Wind Carrier, Van Oord, RWE, Vattenfall, Equinor and more:
The new seafastening guideline is a great example of locking in the potential of an obvious and necessary standardization in the offshore wind industry. The reduced mob & demob durations will result in a higher utilization rate of the installation vessels, reduced CAPEX and reduced unnecessary waste of steel. In short, all stakeholders benefit, and it brings all of us a step closer to fossil freedom.
- Thomas Deelen, Product Portfolio Director T&I, Vattenfall
Collaboration among supply chain stakeholders plays a significant role in promoting innovation and sustainability in offshore wind. The WIS project has brought together industry leaders to develop best practices that have the potential of improving operational efficiency and reducing environmental impact.
- Maria Lindhoff Kjær, Vice President Product Lines, Equinor
Fred. Olsen Windcarrier welcomes initiatives that enables the offshore wind industry supply chain to execute more efficiently, improve sustainability and reduce costs. The Wind Industry Standardization (WIS) represents a valuable step in the right direction.
- Axel Wullf Wathne, Head of Engineering, Fred. Olsen Windcarrier
The ability to reuse equipment and standardize operations across projects is a game-changer. With WIS, we can now execute offshore wind installations faster, more sustainably, and with greater cost efficiency.
- Héloïse Vignal, Vice President - Head of Project Engineering, Cadeler
More Cooperation to come
According to Vestas and Siemens Gamesa this result is the first of many. There are already several ongoing standardization projects. For example, on tower transport equipment and tower stand for pre-assembly.
“There is still significant potential to make the industry more resource- and cost-efficient by maturing the supply chain. This is a shared journey for the entire industry, and as OEMs, we are committed to doing our part.” says Brian Mikkelsen, SVP, Nacelles R&D from Vestas.
”We have several good projects ongoing already, but we don’t have all the answers. We know, that there is great ideas in every step of the supply chain, and we welcome everyone to engage with Energy Cluster Denmark to share ideas and drive progress together.” says Jesper Møller, Chief Engineer Offshore Execution from Siemens Gamesa.
The Wind Industry Standardization (WIS) project is funded by the industry itself, with Siemens Gamesa and Vestas as sponsors and main contributors, alongside a broad range of industry participants. Energy Cluster Denmark are facilitating the collaboration, ensuring strong industry alignment and implementation.
WindEurope Launch event
Join us for the launch of the Seafastening Design Guideline at WindEurope on April 10 from 12:15–13:30 in Meeting Room 18, Bella Center. Key industry players will share how standardization can help accelerate offshore wind deployment. The event is open to all registered EuroWind participants.
Kontakter
Line FlatauCommunication ManagerEnergy Cluster Denmark
Tlf:+45 60191512lfl@energycluster.dkLinks
Om Energy Cluster Denmark:
Energy Cluster Denmark er Danmarks klyngeorganisation og innovationsplatform for den samlede energisektor. Vi hjælper med at facilitere og fundraise
innovationsprojekter, der altid involverer partnerskaber mellem små og mellemstore virksomheder, markedsledende virksomheder og førende forsknings- og videninstitutioner.
Energy Cluster Denmark har ca. 500 medlemmer blandt virksomheder og videninstitutioner. Sammen har vi en samlet portefølje af spændende innovationsprojekter på over 3 mia. kr.
About Energy Cluster Denmark
Energy Cluster Denmark is Denmark’s cluster organization for the entire energy sector, with a vision to make Denmark a global leader in green energy solutions. As a neutral, member-driven innovation platform, it fosters collaborations between companies, knowledge institutions, and public players to drive innovation and strengthen the competitiveness of the Danish energy sector.
The WIS program, sponsored by Siemens Gamesa and Vestas, is one of the initiatives Energy Cluster Denmark facilitates.
Følg pressemeddelelser fra Energy Cluster Denmark
Skriv dig op her, og modtag pressemeddelelser på e-mail. Indtast din e-mail, klik på abonner, og følg instruktionerne i den udsendte e-mail.
Flere pressemeddelelser fra Energy Cluster Denmark
Energy Cluster Denmark udpeges på ny som national klyngeorganisation16.5.2025 08:22:17 CEST | Pressemeddelelse
Danmarks Erhvervsfremmebestyrelse har netop genudpeget Energy Cluster Denmark som national klyngeorganisation for energisektoren i perioden 2025-2028. Med genudpegningen tildeles 100 mio. støttekroner til energiklyngen, der skal fremme fælles innovation mellem danske virksomheder og forskere.
Dansk startup vil transportere CO2 i skibscontainere15.5.2025 06:45:50 CEST | Pressemeddelelse
Den danske virksomhed DecarbonICE vil bruge den globale transport af skibscontainere til transport af CO2 i fast form som tøris. Målet er lettere og billigere fragt af CO2.
Ny bestyrelse i Energy Cluster Denmark12.5.2025 15:26:25 CEST | Pressemeddelelse
Nordic Hydrogen og NorSea Denmark er blandt de nye navne i bestyrelsen i den danske energiklynge. Aktuelt består Energy Cluster Denmarks bestyrelse af 23 medlemmer blandt selskaber og organisationer i energisektoren.
DecomBlades vinder prisen som Årets Innovationsprojekt for banebrydende genanvendelse af vindmøllevinger8.5.2025 13:12:43 CEST | Pressemeddelelse
Med cirka 70% procent af stemmerne fra de knap 300 deltagere på Energy Cluster Denmarks årsmøde i Musikhuset Esbjerg er DecomBlades kåret som Årets Innovationsprojekt 2025.
Ny fælles guideline lanceret i vindindustrien: "Uden standardisering når vi ikke til næste niveau"6.5.2025 17:32:00 CEST | Pressemeddelelse
Siemens Gamesa og Vestas har lanceret en fælles guideline for seafastening med bred opbakning fra vindindustrien.
I vores nyhedsrum kan du læse alle vores pressemeddelelser, tilgå materiale i form af billeder og dokumenter samt finde vores kontaktoplysninger.
Besøg vores nyhedsrum