St-Georges Eco-Mining Corp.
5.6.2024 13:02:28 CEST | ACCESS Newswire | Press release
MONTRÉAL, QC / ACCESSWIRE / June 5, 2024 / St-Georges Eco-Mining Corp. (CSE:SX)(OTCQB:SXOOF)(FSE:85G1) would like to provide an update on the progress of its battery recycling operations and offer some guidance on the progress of other initiatives.
EVSX
Battery Operations
Per the terms of the environmental compliance approval issued to EVSX by the Ministry of the Environment, Conservation and Parks, the financial assurance required by the Ministry is now in place, having been accepted in the form of an all-cash guarantee.
The Company is now in the process of completing the commissioning of its 4,200 tons per year industrial line at its Thorold, Ontario location, for a final inspection by the pertinent regulatory authorities.
Management is now negotiating the form of the battery allocations with its sponsors and partners. It has also reactivated discussions with suppliers that require recycling credits. The aim is to use the results obtained in the first three months of battery processing operations to help finance the installation of the first of the larger multi-chemistry lines in storage at the plant.
Entities with large volumes of lithium batteries are soliciting the Company to provide processing capacity. After obtaining an update to its operational and environmental permits, the Company will be better positioned to enter this market segment. This is expected to occur after accumulating several months of financial and technical data from the operations of its alkaline industrial line.
Management is now planning to use the Thorold plant as its showcase.
All expansion projects outside Thorold are expected to be done via partners, joint ventures, or licensing agreements. With discussions at different stages, the Company is prioritizing potential partnerships with private and para-public entities with a clear and fast track to permitting and in already established adjacent or complementary operations.
St-Georges Metallurgy
Freeing Up Management Resources
EVSX Corp. is the entry point for the Company into the supply of blackmass for St-Georges Metallurgy (SXM), where margins are expected to be significantly more important. Although industrial operations experience exists within the current management, EVSX should transition from the current management to hired operators in the future. This move frees up St-Georges management to focus on deploying SXM's blackmass metallurgical processes where expertise is not interchangeable.
Micronutrient and Soil Regeneration Agreement
SXM has entered into an updated agreement with an industrial farming group to process the initial two years of mainly manganese-zinc-potassium hydroxide blackmass that EVSX operations will generate. The partners expect to create a joint venture following the initial testing period. The product blend design and the request for government certification will allow the joint venture to sell its high-value micronutrient and soil regenerator blends to big box stores. Initial research has shown that in some contexts, these products could bring higher profits than the production of ferro-manganese and zinc. This will provide flexibility to the partners to route the blackmass to the most profitable operations based on market conditions.
U.S. Subsidiary
St-Georges Metallurgy Corp. expects to create a U.S. subsidiary that will allow it to meet some of the requirements for United States Department of Defense Title III grants.
Lithium Technology Licensing Agreement
The Company would also like to disclose that it has entered into an exclusive agreement with LiOH Corp., a corporation created to finance and market SXM lithium technology. Frank Dumas, an officer of St-Georges, is the company's president, and certain officers, directors, and shareholders of St-Georges have become shareholders of the new entity.
The Intellectual Property license is not transferable and is limited to the processing of mining feedstock exclusively. Hybrid operations, from battery blackmass, metal recycling, and other mineral sources supplemented by primary mined material, are not part of the license and are still expected to be operated by SXM.
LiOH will pay all cash disbursements required to finance and operate the initial showcase lithium nitrate and lithium hydroxide operations. The initial budget calls for disbursements of $5m to $8m. No cash commitment from SXM is required. Equipment manufacturers and governments are expected to contribute to portions of the financing.
St-Georges will not have to raise money for this operation, and its contribution is limited to access to its scientists and innovation team. LiOH will finance any potential IP challenge. A timeline established by the partners requires disseminating a feasibility study and starting the preliminary engineering work for the larger industrial plant by March 31, 2027.
St-Georges will receive 8% of the outstanding shares of LiOH either at the time of a public listing or at the start of the commercial operations that coincide with the start of the regular royalty payments.
LiOH will pay an initial advance royalty fee of $125,000 before year-end and will pay advance royalty fees of $125,000 each year until commercial operations start.
Royalty Calculation
For all its operations, LiOH shall pay SX Royalties as follows:
For the period starting from the date on which LiOH starts to process lithium-bearing material until the date the cumulative operations reached the milestone of 10,000 tons of lithium-bearing material being processed in connection with the Manufacture of Licensed Product (the "First Royalty") there are no Royalties payable.
For the period starting from the date on which LiOH reaches the initial milestone of 10,000 tons of lithium-bearing material being processed and for the initial 250,000 tons of lithium-bearing material being processed annually, the Royalties owed per quarter, shall be equal to three percent (3%) of the Net Sales of Licensed Product Manufactured and sold within the relevant quarter and when payment for the product is received.
For the period starting from the second milestone where LiOH reaches an annual processing production for lithium-bearing material in excess of the initial 250,000 tons annually, the excess production of Licensed Product will be applied (the "Second Royalty"), the excess Royalties owed per quarter shall be increased by two percent (2%) for a cumulative total of five percent (5%) of the Net Sales of Licensed Product Manufactured and sold within the relevant quarter on the excess material, with no effect on the initial 250,000 tons of production of lithium-bearing material which will remain under the First Royalties payment structure and remain at three percent (3%).
Royalty payments shall be calculated and accrued on a quarterly basis and pro-rated, as applicable, per calendar year [(i.e., March 31, June 30, September 30, and December 31)] and LiOH shall pay to SX all outstanding amounts within thirty (30) days of the reception of payment for the products sold. LiOH shall deliver a business summary for every quarter that summarizes, among other things, the gross amount billed and calculation of Net Sales for the Licensed Products. Each payment shall be accompanied by a statement indicating the calculation of the Royalties for each Plant in Operation.
Royalty Buy Back Right on "Second Royalty":
During the Second Royalty Term, at any time after a Plant has reached a processing level of 250,000 tons or more of spodumene in connection with the Manufacture of Licensed Products, LiOH shall have the right (the "Royalty Buy Back Option") to repurchase a portion of SX's right, title and interest in and to the Royalties hereunder in consideration of paying CA $25,000,000 (the "Buy Back Price"). Upon payment of the Buy Back Price, the Royalties shall be reduced from five percent (5%) of the Net Sales to three percent (3%) of the Net Sale. LiOH may exercise the Royalty Buy Back Option by delivering to SX a written notice of exercise (the "Royalty Buy Back Notice") at any moment and the buy back of the second royalty will become effective on the 1st day of the following quarter. Thereafter, the Royalties set out in Section 3.2.1(C) shall be reduced to three percent (3%) for the remainder of the Second Royalty Term.
H2SX
Demonstration Plant
The Company is working on a US$7.5m financing for which it has received interest and is initiating due diligence with institutions' placees. Current operations are setting up the demonstration plant in Seoul, South Korea. H2SX is expected to contribute equally to the proposed budget to put the plant into operation with its Korean partner and the South Korean government.
Ownership Dilution
St-Georges expects to have its position diluted by the current financing and might also sell portions of its holding to stay under 20% of the total equity of H2SX.
New Intellectual Property
H2SX expects to receive an exclusive and perpetual license for two new provisional patents covering a newly discovered method to make battery-grade carbon with methane-generated hydrogen as a by-product.
St-Georges Eco-Mining Corp
Québec Exploration
A more comprehensive press release that covers the operations at Manicouagan, an update on permits and technical NI 43-101 reports, and 2024 exploration plans will be issued. It will also include the initial observations on a prospective niobium discovery that is taking shape on the Notre-Dame Niobium Critical Minerals Project.
Iceland Resources
IR is completing due diligence with companies that have shown interest in investing directly into its equity prior to its proposed spin off via a plan of arrangement and the listing of its shares in Europe and North America. The Company is also in the process of assembling a team of seasoned directors and executives in preparation for its next phase of development.
Other Corporate Matters
Fenix Battery Metals Inc.
The Company is currently negotiating with and expects to finalize a detailed agreement with FeNiX Battery Metals, a company led by Enrico Di Cesare, a director and officer of St-Georges Eco-Mining Corp. FeNiX would be responsible for financing all its operations. An equity payment would be received by St-Georges in shares of FeNiX prior to a going public transaction. FeNiX has developed metallurgical technologies that could significantly improve the bottom line and the environmental record of the iron and steel-making industry. The developments for ferro nickel and ferro manganese are of strategic interest for the St-Georges ecosystem.
Financing Offering
The Company is expecting to announce a financing offering for $500k to $750k in the form of a convertible debenture with two half warrants per tranche of unit value of $0.10. The conversion mechanism shall be a discount to market at the time of the conversion. The interest will be paid in shares of the Company on a quarterly basis. The Company expects to announce the details of the financing in a future press release. The proceeds would be used to launch the operations at its Thorold, Ontario plant and for administrative purposes.
ON BEHALF OF THE BOARD OF DIRECTORS
‘Neha Edah Tally"
NEHA EDAH TALLY
Corporate Secretary of St-Georges Eco-Mining Corp.
About St-Georges Eco-Mining Corp.
St-Georges develops new technologies to solve some of the most common environmental problems in the mining sector, including maximizing metal recovery and full-circle battery recycling. The Company explores for nickel & PGEs on the Manicouagan and Julie Projects on Quebec's North Shore and has multiple exploration projects in Iceland, including the Thor Gold Project. Headquartered in Montreal, StGeorges' stock is listed on the CSE under the symbol SX and trades on the Frankfurt Stock Exchange under the symbol 85G1 and as SXOOF on the OTCQB Venture Market for early stage and developing U.S. and international companies. Companies are current in their reporting and undergo an annual verification and management certification process. Investors can find Real-Time quotes and market information for the company on www.otcmarkets.com
Visit the Company website at https://www.stgeorgesecomining.com
For all other inquiries: public@stgeorgesecomining.com
The Canadian Securities Exchange (CSE) has not reviewed and does not accept responsibility for the adequacy or the accuracy of the contents of this release.
SOURCE: St-Georges Eco-Mining Corp.
View the original press release on accesswire.com
To view this piece of content from www.accesswire.com, please give your consent at the top of this page.
About ACCESS Newswire
Subscribe to releases from ACCESS Newswire
Subscribe to all the latest releases from ACCESS Newswire by registering your e-mail address below. You can unsubscribe at any time.
Latest releases from ACCESS Newswire
SK Tes Ireland Achieves ISO Certification Milestone and Recognized in National Digital Infrastructure Report4.6.2026 15:00:00 CEST | Press release
DUBLIN, IE / ACCESS Newswire / June 4, 2026 / SK tes, a global leader in sustainable technology lifecycle services, today announced that its Ireland facility has successfully passed audits for ISO 9001 (Quality Management), ISO 14001 (Environmental Management), ISO 45001 (Occupational Health & Safety), and ISO 27001 (Information Security Management), reinforcing its commitment to delivering consistent, high-quality, safe and sustainable services worldwide. These certifications are standard across SK tes' global network of facilities and form a core part of the company's operating model. As the newest site within this network, Ireland's certification reflects the structured commissioning process that ensures every SK tes location meets the same rigorous international standards - enabling clients to receive a consistent, secure, and compliant service experience, regardless of geography. In parallel, the Irish business has been recognized in the DII Economic Report 2026, published by Digi
Preservica takes AI for Digital Preservation to the next level with powerful new AI Editions4.6.2026 15:00:00 CEST | Press release
OXFORD, UK AND BOSTON, MA / ACCESS Newswire / June 4, 2026 / Preservica, a global leader in AI-powered Active Digital Preservation™, today announced the launch of its new AI Editions that combine human-centric AI tools with the built-in AI capacity to enable archival and records teams to quickly and safely transform their archives at scale. Developed in collaboration with the Preservica user community, the new AI Editions enable teams to process backlogs up to four times faster, meet privacy, accessibility, and FOI requirements, standardize metadata quality, accelerate content enrichment and discovery, and free time for higher-value work. With ample AI capacity included, teams can save significant time - cutting repetitive, manual work and quickly adding new value to their archives every month: Transcribe hundreds of hours of AV content or OCR thousands of scanned images or Identify PII in hundreds of thousands of documents or Standardize metadata across thousands of assets And more "S
Gedeon Richter Highlights Expanding Biosimilars Portfolio and Scientific Engagement at EULAR 20264.6.2026 14:45:00 CEST | Press release
LONDON, UK / ACCESS Newswire / June 4, 2026 / The Biotechnology Business Unit of Gedeon Richter Plc. (Richter) is present at this year's European Alliance of Associations for Rheumatology's (EULAR) European Congress of Rheumatology, underlining its role as a growing contributor to biologic therapies in Europe. The company also hosted a satellite symposium on the opening day, as part of its engagement with the rheumatology community. Richter's presence at EULAR reflects nearly two decades of focused investment following its strategic entry into biotechnology. Today, it operates a fully integrated biosimilars business with a European development and manufacturing network, including facilities in Budapest and Debrecen in Hungary, operations in Germany, and global partnerships supported by over 1,000 biotech professionals. As part of its scientific program, yesterday Richter hosted the symposium "Prevention, better than treatment - insights on inflammatory joint disease and osteoporosis" c
Media Invitation: Fields Medals and Cutting-Edge Math at ICM 2026 in Philadelphia2.6.2026 20:30:00 CEST | Press release
PHILADELPHIA, PA / ACCESS Newswire / June 2, 2026 / Members of the press are invited to the world's most prestigious mathematics conference, which will take place at the Pennsylvania Convention Center in Philadelphia from July 23 to July 30, 2026. Held every four years, the International Congress of Mathematicians (ICM) includes the announcement of the field's top prizes - including the Fields Medals - as well as top talks from leading mathematicians on cutting-edge developments in the field. Staff reporters and freelance journalists can register to attend the conference free of charge through June 22. Media registration includes access to a press conference with the Fields Medalists and other honorees following their announcement during the July 23 opening ceremony. A press room will also be available during the conference. Discounted hotel room rates are available to attendees. For more information, visit the ICM 2026 website or email icmpressinquiries@simonsfoundation.org. The confe
IXOPAY Launches Payments Intelligence and IXONav, an AI Payments Assistant Built to Unlock Real-Time Insights Across the Payments Journey2.6.2026 06:00:00 CEST | Press release
Company's intelligence layer combines AI-driven analytics with anomaly detection to improve merchant payments optimization, performance and revenue outcomes LEHI, UT / ACCESS Newswire / June 2, 2026 / IXOPAY, the performance layer powering global payments for the agentic era, today announced IXOPAY Payments Intelligence, a unified control center that transforms fragmented payment data into real-time, actionable insights. The company also launched IXONav, a new AI agentic navigator built to unlock key insights at every step in the payments journey. By combining AI-driven analytics, anomaly detection and LLM agents, the platform helps merchants uncover optimization opportunities, improve routing performance, increase authorization rates and reduce per-transaction costs. IXOPAY's no-code payments platform unifies payment orchestration, tokenization, and intelligence, and provides merchants with a configurable infrastructure to optimize their payments performance. The IXOPAY Payments Intel
In our pressroom you can read all our latest releases, find our press contacts, images, documents and other relevant information about us.
Visit our pressroom