St-Georges Eco-Mining Corp.
25.3.2024 11:47:31 CET | ACCESS Newswire | Press release
THOROLD, ON / ACCESSWIRE / March 25, 2024 / St-Georges Eco-Mining Corp. (CSE:SX)(OTCQB:SXOOF)(FSE:85G1) is delighted to announce that its wholly owned battery recycling subsidiary, EVSX Corp., has received the Environmental Compliance Approval for its battery processing plant in Thorold, Niagara Region, Ontario. EVSX had sought the Ministry of the Environment, Conservation and Parks' authorization for a waste transfer and processing site for the receipt, transfer, and processing of waste alkaline batteries.
The Company currently has one industrial line installed, allowing for the initial processing of 4,200 tons per year of alkaline batteries that could result in up to approximately 3500 tons of manganese/zinc crude blackmass production annually.
The environmental compliance approval issued to EVSX by the Ministry is subject to certain terms and conditions, including, but not limited to, provisions regarding potential changes of ownership in the future, site visits and inspections, data collection, record keeping and reporting, complaint management, training, spill response and reporting, and the obligation to present a plan for site closure four months in advance, if the Company decides to move its operations in the future.
Some provisions are more restrictive; these sections of the environmental compliance approval are as follows:
Financial Assurance
1. The Owner shall maintain financial assurance, as defined in Section 131 of the Act, in the amount of one hundred ten thousand one hundred seventy-five dollars and zero cents (CAD 110 175). This financial assurance shall be in a form acceptable to the Director and shall provide sufficient funds for the analysis, transportation, Site clean-up, monitoring and disposal of all quantities of waste on the Site at any one time.
2. Commencing on March 31, 2029 and at intervals of five (5) years thereafter, the Owner shall submit to the Director, a re-evaluation of the amount of financial assurance to implement the actions required under Condition 7.1. The re-evaluation shall include an assessment based on any new information relating to the environmental conditions of the Site and shall include the costs of additional monitoring and/or implementation of contingency plans required by the Director upon review of the closure plan and annual reports. The financial assurance must be submitted to the Director within ten (10) days of written acceptance of the re-evaluation by the Director.
3. The amount of financial assurance is subject to review at any time by the Director and may be amended at his/her discretion. If any financial assurance is scheduled to expire or notice is received, indicating financial assurance will not be renewed, and satisfactory methods have not been made to replace the financial assurance at least sixty (60) days before the financial assurance terminates, the financial assurance shall forthwith be replaced by cash.
Hours of Operation
The Owner shall ensure that waste receiving at the Site is restricted to between the hours of 8:30 a.m. to 4:30 p.m. Monday through Sunday.
Approved Waste Types and Waste Screening.
1.The Owner may only accept waste batteries at the Site for waste transfer and/or processing.
Non-alkaline waste batteries may be received at the Site but shall not be processed until such a time as the Owner amends this Approval to permit such activity.
2. The Owner shall ensure all incoming loads are inspected by a Trained Person to ensure only waste approved under this Approval are received at this Site;
3. If any incoming waste load is known to, or is discovered to, contain unapproved waste, that load shall not be accepted at the Site; and
If any unapproved waste is discovered on-site that waste shall be immediately disposed of in accordance with the EPA and Reg. 347.
Approved Waste Quantities
1. The amount of waste that may be received at the Site shall not exceed the amounts identified in the current Design and Operations Report:
A maximum of 4,200 tons per year (an annualized daily average of 12 tons per day), and A maximum of 84 tons per day.
In the event that residual waste and/or processed waste cannot be transferred from the Site, the Owner shall cease accepting any additional waste.
Waste Processing
1. Processing carried out at the Site is limited to the sorting and processing of waste alkaline batteries as described in the Design and Operations Report.
2. Processing shall be conducted by Trained Persons only.
3. The Owner shall ensure the processing equipment is operated in a manner which does not cause an Adverse Effect including, but not limited to, effects from noise and dust.
4. No waste processing other than the processing of alkaline batteries shall be permitted at the Site.
Any processing of other wastes (including waste lithium or non-alkaline batteries) or inclusion of new waste processing equipment shall not be permitted without an amendment to this Approval.
Waste Storage
1. Waste must be stored in accordance with the current Design and Operations Report and at a minimum the Owner shall ensure that:
all activities related to the unloading and storing of incoming waste, in-process waste, processed waste and residual waste shall be conducted indoors at all times;
all waste batteries received at the Site are processed or transferred within one (1) week of receipt; and
processed and/or residual waste (i.e. black mass, steel, brass, plastic and paper) shall not be stored at the Site for longer than thirty (30) days once generated.
2. The maximum amount of waste, including unprocessed waste, in-process waste, processed waste and residual waste that may be stored at the Site at any one time shall not exceed 480 tons including:
86 tonnes of unsorted batteries stored in drums;
72 tonnes of sorted alkaline batteries stored in drums;
18 tonnes of sorted non-alkaline batteries stored in drums;
240 tonnes of black mass stored in bags; and
62 tonnes of processed waste other than black mass, such as steel, brass, plastic and paper.
The Owner shall ensure that all tanks, containers, and storage areas are clearly labelled, and that a sign is posted on each tank, container and storage area indicating the type of waste being stored.
With the reception of this environmental compliance approval, EVSX can now commission the installed line and prepare for the reception of the first containers of batteries to be processed. At this point, management expects to inform its partners and stakeholders of its newly available capacity. EVSX should be able to launch the process leading to the start of the full industrial operations as soon as this process is concluded.
A comprehensive corporate update, including EVSX operations, is forthcoming. This update will cover the Thorold plant, the proposed Italian joint venture for which sites have now been identified and the authorization process clarified, the operational deployment strategy for other jurisdictions, and information regarding the strategies being reviewed to initiate authorization for additional battery chemistries in Ontario and additional jurisdictions under evaluation.
"(…) Receiving the Ontario Government's Environmental Compliance Approval for our battery processing plant in Thorold is a significant milestone, a testament to our team's effort and dedication. (…) The compliance framework provides a manageable foundation upon which we can improve and establish an operation that will not only meet industry standards but also set a new benchmark for the battery processing industry. (…) As we evolve from concept to operations, we recognize the support of our partners and stakeholders. Their support has been a cornerstone of our maturation, and we look forward to deepening these connections. (…) Our strategy brings recycling and processing resources together. From collection to recycling, optimizing every step of the route is crucial. (…) We are currently fielding opportunities to enable us to advance discussions toward tangible relationships, creating a network of alliances that may redefine the industry. (…) As our operations improve in efficiency and we integrate into the market ecosystem, we will collaborate with entities that could traditionally be seen as competitors but that we see as allies. (…) The advantages of working complementarily rather than competitively are immense. (...) Given the diversity of batteries, each demanding a tailored strategy, our approach is designed to ensure we meet industry challenges head-on. (...) Our goal is to build a solid base camp and grow with the market, adding business segments in-house while limiting the financial and logistical resources stress on our organization. (…) The immediate roadmap includes spearheading initiatives with groups and communities to divert batteries from landfills to our recycling facilities, showcasing our circular economy principles. (…) Today's achievement is not the mountaintop but the announcement of an ambitious and necessary ascent. We're not just participating in the industry; we're aiming to redefine its summit. (…)" commented Enrico Di Cesare, CEO of EVSX Corp.
ON BEHALF OF THE BOARD OF DIRECTORS
‘Enrico Di Cesare'
ENRICO DI CESARE
CEO of EVSX Corp, Vice-President R&D & Director of St-Georges Eco-Mining Corp.
About St-Georges Eco-Mining Corp.
St-Georges develops new technologies to solve some of the most common environmental problems in the mining sector, including maximizing metal recovery and full-circle battery recycling. The Company explores for nickel & PGEs on the Manicouagan and Julie Projects on Quebec's North Shore and has multiple exploration projects in Iceland, including the Thor Gold Project. Headquartered in Montreal, St-Georges' stock is listed on the CSE under the symbol SX and trades on the Frankfurt Stock Exchange under the symbol 85G1 and as SXOOF on the OTCQB Venture Market for early stage and developing U.S. and international companies. Companies are current in their reporting and undergo an annual verification and management certification process. Investors can find Real-Time quotes and market information for the company on www.otcmarkets.com
Visit the Company website at www.stgeorgesecomining.com
For all other inquiries: public@stgeorgesecomining.com
SOURCE: St-Georges Eco-Mining Corp.
View the original press release on accesswire.com
To view this piece of content from www.accesswire.com, please give your consent at the top of this page.
About ACCESS Newswire
Subscribe to releases from ACCESS Newswire
Subscribe to all the latest releases from ACCESS Newswire by registering your e-mail address below. You can unsubscribe at any time.
Latest releases from ACCESS Newswire
Kraft Heinz, Braskem, and Tenaris to headline OMP Conference São Paulo 202617.2.2026 15:00:00 CET | Press release
Global industry leaders showcase real-world results and AI-driven supply chain planning innovations SÃO PAULO, BR / ACCESS Newswire / February 17, 2026 / OMP, a leading provider of AI-powered supply chain planning solutions, brings its REAL conference series to Latin America with a one-day event in São Paulo on April 16, 2026. The conference will bring together Fortune 500 leaders to share how they are transforming global operations through digital innovation. Under the theme "Real expertise. Real solutions. Real results," the conference focuses on the practical application of AI in complex supply chain environments. The agenda is anchored by three global powerhouses who will provide a "behind-the-scenes" look at their digital transformation journeys in partnership with OMP's Unison Planning™: Kraft Heinz, a global food and beverage company, will demonstrate how data-driven planning, AI-enabled optimization, and end-to-end visibility are building a more agile and sustainable value chai
Supported by U.S. Polo Assn., the 2026 U.S. Open Women's Polo Championship(R) Concludes with Victory Eastern Hay the Champion17.2.2026 13:00:00 CET | Press release
WEST PALM BEACH, FL / ACCESS Newswire / February 17, 2026 / U.S. Polo Assn., the official sports brand of the United States Polo Association (USPA), proudly supported the 2026 U.S. Open Women's Polo Championship®, which concluded on February 15 at the USPA National Polo Center (NPC) in Wellington, Florida, on the iconic U.S. Polo Assn. Stadium Field. Widely regarded as the most prestigious women's polo tournament in the United States, the championship brought together the sport's top athletes for three weeks of elite competition at the heart of American polo.1. Victory Eastern Hay proudly displaying their trophy as winner of the 2026 U.S. Open Women's Polo Championship at the USPA National Polo Center 2. Victory Eastern Hay Team on horseback (#1 Rebecca Schmeits, #2 Aspen Tinto, #3 Hazel Jackson, #4 Milly Hine) at the 2026 U.S. Open Women's Polo Championship 3. La Dolfina Team presents a donation to their charity of choice, Polo Players Support Group, provided by U.S. Polo Assn., at th
Camino Intercepts High-Grade Copper with 83.5m at 0.94% Cu including 7.1m at 2.13% Cu at Los Chapitos, Peru17.2.2026 12:00:00 CET | Press release
VANCOUVER, BC / ACCESS Newswire / February 17, 2026 / Camino Minerals Corporation (TSXV:COR)(OTCID:CAMZF) ("Camino" or the "Company")is pleased to announce the exploration results from Phase 1 of the recent drilling campaign at its Los Chapitos copper project ("Los Chapitos" or the "Project") in Peru. This news release reports the results from eight drill holes completed along the Diva trend corridor, where drilling activities focused on several targets with the objective of expanding the known mineralized body and improving the understanding of the scale and continuity of the mineralized system. Los Chapitos is Camino's second copper project with partner Nittetsu Mining Co, Ltd. ("Nittetsu"), who is completing a 35% earn-in interest in Los Chapitos after investing CAD $10 million and after the completion of Phase 2 of the current drilling campaign (see news release dated June 14, 2023). Camino is also advancing its Puquios Copper Project in Chile with Nittetsu Mining towards mine cons
Datavault AI Updates Revenue Estimates by Approximately 30% at $38M to $40M17.2.2026 12:00:00 CET | Press release
PHILADELPHIA, PA / ACCESS Newswire / February 17, 2026 / Datavault AI Inc. (NASDAQ:DVLT) ("Datavault AI" or the "Company"), a leader in data monetization, credentialing, digital engagement and real-world asset (RWA) tokenization technologies, today announced its updated preliminary (unaudited) fiscal year 2025 revenue is estimated to be $38 to $40 million, exceeding its prior estimate of $30 million by up to 33%. At its midpoint, estimated FY-25 revenue represents approximately 1,300% growth year-over-year The Company attributed this revenue growth to its customer tech-licensing fees, and its Data Science Group's tokenization and monetization services. Further, Datavault AI reaffirmed its anticipated FY-26 revenue of $200 million, which, if achieved, would represent a year-over-year increase of 400% to 440%. KEY FINANCIAL METRICS FY 2025 (Preliminary, Unaudited): Estimated Revenue: $38-$40 million Prior Estimate: $30 million Incremental Change: +$8-$10 million (+27% to +33%) Midpoint:
Skymantics Europe Leverages DataGenesis to Power Next-Gen European Digital Twins with High-Fidelity Synthetic Populations16.2.2026 11:00:00 CET | Press release
ZARAGOZA, ES / ACCESS Newswire / February 16, 2026 / Skymantics Europe's DataGenesis platform supports the evolution of European Digital Twins. By providing high-accuracy, high-resolution synthetic population datasets, DataGenesis enables the simulation of complex demographic, socioeconomic, and health attributes, allowing for precise future scenario planning and more resilient policy-making across the continent. As Europe moves into a more sophisticated phase of digital modeling, the need to integrate the "human dimension" into Earth-system and urban models is paramount. DataGenesis addresses this by generating "digital twins" of populations that maintain the statistical integrity and multidimensional complexity of real-world communities-without utilizing or exposing sensitive personal information. Integrating Human Dynamics into Digital Ecosystems Skymantics' DataGenesis platform bridges the gap between environmental data and societal impact. Its mature model-based AI approach provid
In our pressroom you can read all our latest releases, find our press contacts, images, documents and other relevant information about us.
Visit our pressroom