The Danish Energy Agency initiates the second public consultation regarding the plan for Hesselø Offshore Wind Farm
Call for remarks on the Strategic Environmental Assessment (SEA) of the plan for Hesselø Offshore Wind Farm (OWF). A public meeting about the consultation material will be held in Gilleleje on 19 March 2024.
The Danish Energy Agency invites the public, companies, authorities and other interested in the coming Hesselø OWF to submit remarks on the SEA of the plan for the revised southern location of Hesselø OWF.
The public consultation of the revised SEA of the plan for Hesselø OWF runs from the 5 February to 5 April 2024.
In connection with the consultation, a public meeting will be held in Gilleleje, where the results of the environmental report will be presented. The public meeting will be held on 19 March from 16.00 - 19.00 in Kulturhavn Gilleleje, Peter Fjeldstrup's vej 12, 3250 Gilleleje. There will be a presentation at 17.00. It is not necessary to register for the public meeting.
Read relevant hearing material, information on how to submit inputs to the hearing etc. (Link in danish)
The further process for Hesselø OWF
After the consultation, the Danish Energy Agency will examine the remarks, and if necessary update the plan accordingly. Hereafter, the Danish Energy Agency will make a SEA Summary Statement and publish the final plan.
In parallel to the SEA, Energinet (Danish TSO) is conducting an Environmental Impact Assessment (EIA) for the land-based part of the project. The Danish Environmental Protection Agency expects mid-2024 to issue the EIA-permit (§ 25 of the Danish Environmental Assessment Act) for the land-based part of the project, provided that the EIA-process allows the project to be carried out.
The final tender material is expected to be published during the spring of 2024, with an expected final tender deadline in February 2025. The EIA of the sea-based part of the project is expected to be carried out in 2025-2027 when the winner of the tender for Hesselø OWF has been found: the scoping phase is expected to be in 2025 and the 2nd public consultation on the EIA report is expected to be in 2027. Later in 2027, the Danish Energy Agency expects to issue the construction license (EIA-permit) for Hesselø OWF, provided that the EIA-process allows the project to be carried out.
Facts
- Hesselø OWF will have an installed capacity of 800 – 1,200 MW.
- The turbines will be located in Hesselø Bay in the Kattegat at a distance of approximately 30 km from Zealand, 30 km from Anholt, 35 km from Djursland and 33 km from Sweden.
- Offshore export cables will run to the landfall at Gilbjerg Hoved in North Zealand. Near Pårup, a new high voltage power station will potentially be constructed. From the station, the electricity will be exported through onshore-buried cables towards the existing high voltage power station Hovegaard north of Ballerup. This station will be extended.
- Deadline for full commissioning of the wind farm is by the end of 2029.
Contact
Special Advisor, Randi Lucie Aliaga (rla@ens.dk), (+45) 33 92 78 35
Advisor, Anders Møller Jørgensen (anmj@ens.dk), (+45) 33 95 51 13
Kontakter
Ture Falbe-Hansen
Tlf:+45 2513 7846tfh@ens.dkPress contact (phone calls only):
Tlf:+45 33 95 08 00Følg pressemeddelelser fra Danish Energy Agency
Skriv dig op her, og modtag pressemeddelelser på e-mail. Indtast din e-mail, klik på abonner, og følg instruktionerne i den udsendte e-mail.
Flere pressemeddelelser fra Danish Energy Agency
New report shows the way for China's green energy transition13.11.2024 07:00:17 CET | Pressemeddelelse
As the world's largest CO2 emitter, China plays a crucial role in reducing global emissions. The country's massive expansion of solar and wind power is the right way to go, though energy efficiency and market mechanisms must be improved if the goal of carbon neutrality is to be achieved. This is according to a new Chinese report to which Danish experts have contributed significantly and which is actively used in the development of Chinese energy policy.
Two companies want to store CO2 in the Danish subsurface11.11.2024 12:29:02 CET | Pressemeddelelse
The Danish Energy Agency (DEA) has received two applications from companies that want to explore the potential for storing CO2 in the subsurface in an area close to Thorning.
Danish Energy Agency presses the start button for billion-dollar tendering procedure for carbon capture and storage9.10.2024 10:31:24 CEST | Pressemeddelelse
The new CCS Fund has DKK 28.7 billion (USD 4.2 billion) to secure capture and storage of CO₂ from as early as 2029, and to help Denmark along its path to climate neutrality. The deadline for applying for participation in the tendering procedure is 25 March 2025.
Invitation to the launch of the Danish CCS Fund and NEKST Implementation Forum for CCS3.10.2024 13:49:05 CEST | Nyhed
The Ministry of Climate, Energy and Utilities and the Danish Energy Agency invite all actors to attend the launch of the Danish CCS Fund and the new industry dialogue forum, NEKST Implementation Forum for CCS on Wednesday October 9 at 10.30-11.30 am.
The Danish Energy Agency opens applications for exploration and CO2 storage in the Thorning area30.9.2024 10:11:56 CEST | Nyhed
The Danish Energy Agency opens a licensing round for exploration and utilisation of the subsurface for geological storage of CO2 in the Thorning area today. At the same time, the agency invites you to an information meeting about the tender on 3 October 2024.
I vores nyhedsrum kan du læse alle vores pressemeddelelser, tilgå materiale i form af billeder og dokumenter samt finde vores kontaktoplysninger.
Besøg vores nyhedsrum