After the conclusion of a historic 9 GW offshore wind agreement The Danish Energy Agency invites potential bidders to a market dialogue regarding the new tender framework
The government and a broad majority of political parties have made an agreement, establishing the framework for the coming 9 GW offshore wind tenders, with operations starting in the end of 2030 at the latest. The Danish Energy Agency is currently working on converting the agreed upon requirements into transparent tender conditions and the next step will be a market dialogue for potential bidders.

On May 30th 2023 the government and a broad majority of political parties concluded a supplementary agreement on tender frameworks for 6 GW of offshore wind and 3 GW at Bornholm Energy Island. The agreement secures the framework for the upcoming 9 GW offshore wind tenders.
With the supplementary agreement in place, the Danish Energy Agency is already working to convert the agreed access requirements into transparent tender conditions. An important part of this is the market dialogue that the Danish Energy Agency is currently preparing. Over the summer, the Danish Energy Agency plans to invite to a market dialogue with the aim to get constructive input on the tender material and on how the decided tender frameworks are to be converted to a tender material. The concrete implementation of the new decided requirements will also be discussed.
The preliminary studies of the seabed, nature, environment, etc. is already underway, and the Danish Energy Agency is in the process of preparing the tender material.
Possibility of overplanting increases the total capacity
The offshore wind installations on Nordsøen I, Kriegers Flak II and Kattegat II are given the option of free overplanting with the agreement - i.e. freedom to set up more offshore wind than has been politically agreed upon. For Hesselø and Bornholm Energy Island, the strategic environmental assessments are already so far in the process that only a more limited overplanting can be permitted. This means a total capacity of 1.2 GW for Hesselø and 3.8 GW for Bornholm Energy Island. Overall, the 9 GW can thus become 14 GW – and perhaps even more.
Together with consultants, the Danish Energy Agency has prepared a large number of analyses, which lay the professional basis for the decisions regarding the 9 GW of offshore wind. See the most important of the analysis reports on the Danish Energy Agency's website:
- Planlægning af fremtidens havvindmølleparker | Energistyrelsen
- Miljøvurderinger - Energiø Bornholm | Energistyrelsen
Read the agreement (in Danish).
Read the Ministry of Climate, Energy and Supply's press release (in Danish).
Facts:
The 9 GW are located as follows:
- Minimum 3 GW at Energiø Bornholm
- Minimum 3 GW in the North Sea I
- Minimum 1 GW at Kattegat II
- Minimum 1 GW at Kriegers Flak II
- 0.8-1.2 GW at Hesselø.
Kontakter
Ture Falbe-Hansen
Tlf:+45 2513 7846tfh@ens.dkFølg pressemeddelelser fra Danish Energy Agency
Skriv dig op her, og modtag pressemeddelelser på e-mail. Indtast din e-mail, klik på abonner, og følg instruktionerne i den udsendte e-mail.
Flere pressemeddelelser fra Danish Energy Agency
China may reach its climate goals ahead of schedule, according to New report9.12.2023 17:20:15 CET | Nyhed
China could potentially break the trend of its CO2 emissions from the energy sector before 2030 and its energy supply could become CO2-neutral well before planned. This is demonstrated in a new report presented today at the UN Climate Summit, COP28. The report was prepared by Chinese authorities with assistance from Danish experts.
The Danish Energy Agency invites potential applicants to an information meeting about the upcoming application process regarding licenses for exploration and storage of CO2 onshore8.12.2023 11:47:59 CET | Nyhed
Before the end of 2023, The Danish Energy Agency will open a licensing round for exploration and storage of CO2 onshore. Therefore, the Danish Energy Agency now invites potential applicants to an information meeting about the application process.
The Danish Energy Agency opens consultation on an amended electricity market bidding zone configuration around Energy Island Bornholm27.10.2023 12:01:34 CEST | Nyhed
Energinet (the Danish TSO) has identified a structural congestion in the electricity transmission network that connects Bornholm Energy Island to Zealand and Germany. As the main rule, bidding zone borders must be drawn on structural congestions in the electricity transmission network. To facilitate this, the Danish Energy Agency makes the decision on an amended bidding zone configuration open for consultation.
The first PtX tender in Denmark has been determined: Six projects will establish electrolysis capacity on more than 280 MW27.10.2023 10:03:10 CEST | Pressemeddelelse
The Danish Energy Agency has concluded the Power-to-X Tender and six projects will win the State Aid. Four different companies are behind the six winning projects and can now start building up the production of green hydrogen in Denmark.
The Danish Energy Agency postpones the second tender round of CO2 storage licenses in the North Sea11.8.2023 15:34:22 CEST | Nyhed
The second tender round for offshore licenses for exploration and use of the subsoil for the geological storage of CO2 in the North Sea is postponed. The tender was set to open on August 15th 2023 according to the executive order on CO2 storage license tenders.
I vores nyhedsrum kan du læse alle vores pressemeddelelser, tilgå materiale i form af billeder og dokumenter samt finde vores kontaktoplysninger.
Besøg vores nyhedsrum